MS Project Calendars

Tel: 020 7920 9500
Email: info@projecttraininglondon.co.uk

 
 
Project training courses in London

Home

Project Beginners Training Course

Project Advanced Training Course

Project Bespoke Training Course

Project Crash Course

MS Project Training Manuals

MS Project Books

Contact Project Training London

Project Training London

You can now download our Project 2010 Training Manual for free!

Free Project 2010 Manual!

MS Project How To Topics

MS Project Tips and Tricks

London Project Training Courses
MS Project Forums
MS Project Blogs
Project training courses in London

MS Project Calendars

 

The Default Working Calendar is used by MS Project to calculate all Timescales and Resource costs. It defaults to a working day of 8 hours with the working hours 0800 to 1200 and 1300 to 1700.

You can create your own calendar with your own particular times. If this is not a standard 8-hour day you must remember to tell MS Project what the standard day is. Each resource you add will be based on the calendar you select when you start your project.

Depending on the nature of your project you may find that the base calendar and standard 8-hour day is satisfactory. A full day’s work is considered as two shifts¾one in the morning and one in the afternoon. You can use the From and To text boxes in the Working Time area to specify up to three shifts. Selecting Default restores selected days and working hours to their default settings.

Resource calendars deal specifically with resources¾that is, working hours, working days, and vacations on an individual basis. Resource calendars are created automatically when a resource is added to the pool. Users do not create resource calendars. It is up to the user to attach a resource to a specific base calendar.

 
 
 

 